Two summers of detours around Highway 55 and County Road 73 are almost over. The project behind them is called Station 73 TRIP, short for Transit and Regional Improvement Program, and the name points at the park-and-ride. The longest-lasting change for Plymouth is the pedestrian tunnel under Highway 55. Before it, people on foot and on bikes had no direct, safe way across the highway.
The tunnel carries a new 1.2-mile section of the Eagle Lake Regional Trail, which runs from the Luce Line Trail to 1st Avenue North. Three Rivers Park District has already taken this trail through 90 percent design for its next section and plans to build it in 2027. The city's project, which was planned around buses, ended up building the first finished section of a trail meant to run north and south through western Hennepin County.
Highway 55 Had No Safe Way Across on Foot
The city's project page describes the old setup plainly. Pedestrians and bicyclists near Highway 55 and County Road 73 had "no direct or safe route" across the highway to reach city parks, the regional trails, the Station 73 transit facility, or nearby businesses. The roads around the interchange were laid out in ways that slowed traffic and caused safety problems for drivers, Plymouth Metrolink buses, and anyone walking or biking.
Mayor Jeff Wosje's column in the November/December 2026 Plymouth News names the tunnel first among the improvements:
"Prior to the tunnel, the existing area of Highway 55 and County Road 73 posed a variety of safety hazards for pedestrians and bicyclists. The underpass offers safer access to city parks, area neighborhoods, regional trails, the Station 73 transit facility, and nearby businesses."
His list matches the list on the city's project page, with the crossing at the top.
What Got Built Around the Crossing
Most of the other work was there so the crossing could function. The realigned roads, the roundabouts, and the new bus stops all sit around the spot where the trail goes under the highway.
| Piece | What the city lists | Where it stands |
|---|---|---|
| Highway 55 | About 3,000 feet reconstructed, new eastbound and westbound bus stops | Highway reopened Nov. 12, 2025, after last summer's closure, and the city says it will stay open during the 2026 work |
| Pedestrian tunnel | Trail underpass beneath Highway 55 | Described as installed in the mayor's fall column |
| County Road 73 | Realigned from Highway 55 to Sunset Trail | Open to the public as of Sept. 15, 2026 |
| Roundabouts | County Road 73/Sunset Trail, South Shore Drive/10th Avenue, Zachary Lane/Sunset Trail | Mayor's column describes the first two as installed |
| South Shore Drive and 10th Avenue | About 1,500 feet reconstructed | Closed to through traffic as of Sept. 15, with reopening expected later this fall |
| Eagle Lake Regional Trail | About 1.2 miles, Luce Line Trail to 1st Avenue North | Listed as constructed in the mayor's column |
The city's Sept. 15 bulletin says County Road 73, Zachary Lane, Sunset Trail, and the frontage road south of Highway 55 and west of County Road 73 were open. Old County Road 15, South Shore Drive, and 10th Avenue stayed closed to through traffic, though local and business access was kept open. That is the newest road update on the city's project page. Check there before taking South Shore Drive this week.
Why a Plymouth Intersection Drew Regional Money
The funding shows that this is regional infrastructure. Sun Sailor reports a total of $34.95 million. The largest share is a $15 million federal RAISE grant, plus more than $5 million in state matching funds. Plymouth's own local funds came to nearly $2.4 million, alongside $6 million from Plymouth Transit. The rest came from the Metropolitan Council, MnDOT, Hennepin County, and Three Rivers Park District. Several of those amounts were routed through Three Rivers specifically, including $800,000 from regional solicitation and $750,000 from the park district's own capital plan.
In other words, the federal grant alone is roughly six times what Plymouth put in from local funds. A park district that runs trails across the metro also has money in a road project inside Plymouth. Those agencies are paying for one link in a larger network. When the Star Tribune covered the start of construction in June 2025, it called the work a $25 million redo. The higher Sun Sailor total is the more recent of the two figures.
The Unfinished Work Is Waiting on the Trail
If the trail is the main point of the project, it makes sense that the remaining work depends on it. South Shore Park is the clearest example.
Plymouth Parks & Recreation renovated South Shore Park this year. The work included a new playground, a relocated basketball court, picnic tables under the gazebo, bike racks, a drinking fountain, and new signage. In the city's Oct. 19 park project update, the last signs had gone up the week before. The only item left is restoration work that "will take place after the trail is paved as part of the Station 73 project." Three Rivers' 2021 long-range plan routes the regional trail along South Shore Drive from the Luce Line to 10th Avenue, then along 10th Avenue to Highway 55, through South Shore Park between 11th and 10th avenues. The park's last step depends on that trail paving.
The same is true at the transit center. According to the mayor's column, crews still have to finish the Station 73 site improvements:
- Wayfinding signage
- A bike fix-it station
- An electric bike and scooter charging area
- A dedicated area for ridesharing and ride hailing
Three of those four items serve people arriving by bike, scooter, or on foot. When they are done, the park-and-ride becomes a trailhead as well as a bus stop.
Bus riders are in a temporary arrangement for now. Starting Sept. 15, a city rider alert moved pickups to a temporary area at the new cul-de-sac near the west corner of the Park and Ride while the ramp entrance is under construction. The change covers Plymouth Metrolink Routes 774, 776, 777, and 795 and all Click-and-Ride buses. Metrolink is run by the city, with express routes to downtown Minneapolis and the University of Minnesota.
Where the Trail Goes After 1st Avenue North
At 1st Avenue North, the new section stops and the Three Rivers project begins. On its Eagle Lake Regional Trail page, the park district describes a paved, off-road, multi-use trail running north and south through Plymouth and Minnetonka. It will follow the public right-of-way along Plymouth Road, South Frontage Road, and Hopkins Crossroad/Zachary Lane. A public open house on the draft design was held Sept. 22, 2026, and the 90 percent design plans are posted in the page's documents section.
Construction is planned for 2027. When it is done, the trail will connect the Luce Line and Lake Minnetonka regional trails and reach Minnetonka Mills Park, Big Willow Community Reserve, and the Minnetonka Township Loops Trails Corridor. The long-term route goes farther. Three Rivers' plan treats the whole corridor from Eagle Lake Regional Park to Bryant Lake Regional Park in Eden Prairie as one route, split into two named trails for design and construction.
Toward the north, the same long-range plan names Timber Shores Park, Zachary Playfield, and Mission Hills Park along the Zachary Lane trail corridor, which connects to the Bassett Creek and Medicine Lake regional trails. The Highway 55 tunnel is the crossing that links those northern destinations to the Luce Line and to the Minnetonka section going in next year.
Using the Area This Fall
Construction is not quite finished, so here is what helps for now:
- Driving: County Road 73, Zachary Lane, and Sunset Trail were open as of Sept. 15. South Shore Drive, 10th Avenue, and Old County Road 15 were expected to reopen later in the fall. The project page has the current status, and the project hotline is 763-251-1010.
- Riding Metrolink: Board at the temporary cul-de-sac pickup near the Park and Ride's west corner until the ramp entrance work ends.
- Getting on the Luce Line: The Minnesota DNR lists a Luce Line State Trail parking access in Plymouth off 10th Avenue North and Vicksburg Lane.
- South Shore Park: The playground, court, and gazebo are finished. Expect restoration crews to return once the trail through the park is paved.
- Following the 2027 section: The Three Rivers project page has the route map and design plans for the trail south of 1st Avenue North.
If you live near Highway 55 and County Road 73, or you're looking at homes along the coming Eagle Lake trail route, Ryan Johnson Group can give you a candid local read on what the finished work means for your property. Contact us whenever the questions come up.