The Green Line Trains Are Already Running Through Eden Prairie. Here's What Happens Before Riders Board

"The challenge is that it kind of looks like it's done, but it's not done." Green Line Extension project director Jim Alexander said that at a December 2025 oversight meeting. He had ridden his bicycle there.

Ten months later, it still looks done. Stations are standing, the wires are up, and trains with nobody aboard keep passing the Costco on Technology Drive. On Sept. 26, Metro Transit finally gave a date. The extended METRO Green Line will open to passengers on June 12, 2027. That leaves about eight months. Most of the work in those months is about where the trains meet cars, bikes and people on foot, and four of those places are on Eden Prairie streets.

Eden Prairie Has Had Trains the Longest

The test trains aren't new here. In an article published in January 2026, Eden Prairie Local News reported that test cars began crossing Technology Drive "in October." According to the same report, the first light rail train to cover the full 14.5 miles between Target Field and SouthWest Station made the trip on Oct. 14, towed by a diesel car mover. Testing is split into three phases. Eden Prairie was in the first one, so Eden Prairie streets have had moving trains longer than most of the corridor.

An independent readiness review dated May 26, 2026 lays out the schedule:

  1. Phase 1, July 2025 to July 2026. SouthWest Station to the Beltline interlocking, covering most of the line through Eden Prairie, Minnetonka, Hopkins and St. Louis Park.
  2. Phase 2, July to September 2026. The Minneapolis stretch between Bryn Mawr and Target Field, where the new line connects to existing systems.
  3. Phase 3, September to December 2026. The full corridor end to end, SouthWest Station to Target Field. This phase is underway now.
  4. After that, handover. The reviewer found testing on schedule to finish by December 2026, with "full conveyance to rail activation activities" to follow.
  5. Pre-revenue operations, then June 12, 2027. Once the systems contractor turns the corridor over, Metro Transit runs its own testing and training before passengers board.

No public source we found gives a date for the handover or for the start of pre-revenue operations. The Metropolitan Council says only that trains should be on the tracks every day from October 2025 until opening, and that testing happens on most weekdays.

Testing is big because there's a lot to check. As of December 2025, the project expected to need more than 1,500 train runs. Those runs cover crossover switches, track alignment, power delivery, clearances, communications, and the signals at street-level crossings. The list adds up to about 7,000 point-to-point device tests and another 2,000 to 3,000 secondary checks, repeated day and night through every season. Eden Prairie has now seen nearly a full year of that.

Four Crossings Where the Testing Meets Your Errands

Most of the corridor is separated from traffic by bridges and tunnels. The line has 14 at-grade crossings, where trains and cars share the road surface, and Eden Prairie Local News counts four of them in Eden Prairie.

Crossing What's next to it Why it matters
Technology Drive at Flying Cloud Drive Costco and Asia Mall parking lots Busiest of the four. 11,640 vehicles a day in 2024
Town Center Drive Redstone American Grill The Met Council's crossing map labels this area Eden Drive
Viking Drive stub off Flying Cloud Drive Holiday Inn and Marriott hotels Short connector that hotel traffic uses
West 70th Street Golden Triangle The new street extension is tied to Golden Triangle and City West station access

The two sources name the second crossing differently, so look for both names on signs and maps. For crash history, the Technology Drive crossing had 24 reported crashes at or near the intersection from 2021 through 2025. Nearby, at Technology Drive and Prairie Center Drive by the SouthWest Station complex, the count was 68. Before any trains ran, the Costco crossing was the quieter of those two intersections.

Even so, it's the crossing officials have talked about most. In December 2025, then-Minnetonka Mayor Brad Wiersum told the project's oversight committee that he shops at the Eden Prairie Costco and that "Technology Drive makes me the most nervous." Outreach manager David Davies called it one of the project's highest priorities. He said it could get more signage and in-person staff once regular service starts, and that variable message signs were planned for Technology Drive. Eden Prairie Local News' January report has the full exchange.

What the Gates, Bells and Speeds Mean Right Now

The trains aren't all moving the same way during testing. For "dead wire" testing, a railcar mover pulls the trains at about 2 to 5 miles per hour to check clearances and the overhead wire. Under their own power, during "live wire" testing, they can reach 55 miles per hour. If you got used to a slow towed train last fall, you may now see one going much faster.

Some things at the Eden Prairie crossings only happen during testing. The City of Eden Prairie's testing notice warns that warning lights, bells and gates can activate even when no train is in sight. They're being tested too. The Met Council lists the noise to expect: wheels, horns, bells, crossing warnings and the public address systems at stations.

The Met Council's systems testing page answers a few other common questions:

  • Trails stay open. You can ride the trails during testing, but expect occasional stops at crossings.
  • Photos are fine. You can photograph and film the trains from public areas at a safe distance.
  • No early rides. The public can't ride until the system is ready for revenue service.
  • Flashing lights mean stop. Trains can come from either direction, and the only safe places to cross are marked crossings.

Some test cars carry the safety message on the outside. One was wrapped with "Never try to beat a train! Stop when flashing! Listen up!" and another with "STAY SAFE" and "OPENS IN 2027."

The Stations Sit Next to Places You Already Use

Eden Prairie gets four stations: SouthWest, Town Center, Golden Triangle and City West. Each one is near a spot Eden Prairie residents already know.

SouthWest Station is the end of the line. It's set up as a bus and rail transfer hub with park-and-ride, and the Met Council describes it as next to Purgatory Creek's conservation area, a seven-acre park and walking trails. From there, the Green Line will connect to downtown Minneapolis and then on to Union Depot in St. Paul. At Target Field Station, riders can transfer to the Blue Line toward MSP Airport and Mall of America.

Town Center Station is a short walk from Eden Prairie Center, Lake Idlewild and Purgatory Creek Park. The mall already had a Green Line testing sign on New Year's Eve, near the Potbelly on the second level.

Golden Triangle Station serves the employment district. Local reporting names Fox & The Grouse apartments, Aldevron and SunOpta as neighbors. The city approved a multiuse trail, benches and streetlights along 0.8 miles of Shady Oak Road to improve access to the station. Those plans are from 2025. We found no 2026 source confirming that every trail segment around the station is open.

City West Station sits between Highway 62 and Optum's corporate campus, a little east of Shady Oak Road. Optum donated land for the station and its pedestrian walkways. An Eden Prairie resident told Eden Prairie Local News she plans to walk to City West and take the train to Minneapolis for occasional getaways.

The Line Is Already Paying Eden Prairie Back

Development along the line is already showing up in public revenue, months before the first passenger rides. At the Sept. 26 event, Hennepin County Board Chair Irene Fernando said corridor development from Minneapolis to Eden Prairie is generating $35.7 million in property tax revenue in 2026, revenue she described as "not falling on existing property tax owners." She said the City of Eden Prairie will get $1.6 million of that. The whole project cost $2.86 billion. That puts one year of corridor tax revenue in proportion to the overall bill.

The next possible project is next to Town Center Station. A developer has shown housing, retail and office concepts for the empty former JCPenney site at Eden Prairie Center, but as of July 2026 no final plan or timeline had been reported. The city has until Dec. 31, 2028, to set up a tax increment financing district for mall redevelopment. In May, Eden Prairie Local News reported the city's view that the mall is close to Town Center Station, so some additions there could drive light rail ridership. That deadline is about a year and a half after opening day. Eden Prairie should see how the trains get used before anything is decided for that site.

Until opening day, the gates on Technology Drive will keep coming down for empty trains. Each of those runs is part of the testing that has to be finished before passenger service starts June 12, 2027.

A new transit line raises practical questions for people who live near it, whether that's their commute or what the city plans to build near the stations. If you'd like to talk through how the Green Line fits into your plans in Eden Prairie, Ryan Johnson Group is happy to have that conversation, now or after the first train leaves SouthWest Station. Contact Us.

This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.

Let’s Get Started

We pride ourselves in providing personalized solutions that bring our clients closer to their dream properties and enhance their long-term wealth.

Follow Me on Instagram